Renewable Energy · Intermediate level · 3 min read ·

What are P50 and P90 scenarios?

P50 and P90 are two readings of the same production projection. P50 is the value expected to be exceeded in half of the years: the central scenario. P90 is the conservative one, expected to be exceeded 9 years out of 10. The gap between them shows how uncertain the projection is.

In 30 seconds

  • P50 is exceeded in half the scenarios; P90 in nine out of ten.
  • P90 is always lower than P50: it's the prudent reading.
  • More uncertainty in the sun or the data pushes the two values further apart.
01

Why should you care?

A production projection isn't a fixed number: the sun changes from year to year. P50 and P90 show you the center and a reasonable floor.

  • You know whether a production figure is the central or the prudent one.
  • You see how far a bad year's energy could move from a normal one.
  • You compare projects knowing which scenario each one uses.
02

Think of it as your commute to work

Half of the days you get there in 30 minutes or less: that's your P50. But for an important meeting you leave 40 minutes ahead, because that gets you there on time 9 days out of 10: that's your P90. Same trip, two ways to plan.
03

How does P50 and P90 scenarios work?

  1. 1

    Production is simulated

    Software such as PVsyst uses many years of sun data, the design and the losses to estimate annual energy.

  2. 2

    The P50 comes out

    It's the central value: half the years are expected to produce more and half less.

  3. 3

    Uncertainty is measured

    How much the sun varies between years is combined with the margin of error in the data and the model.

  4. 4

    The P90 is calculated

    That uncertainty is taken off the P50 to reach a value exceeded 9 years out of 10.

The formula

P90 ≈ P50 × (1 − 1.282 × σ)

P50
= annual production in the central scenario
σ
= combined uncertainty, as a percentage of P50
1.282
= statistical factor for a 90% probability
04

An example with numbers

A 1 MWp system with a P50 of 1,314 MWh a year, as in the GW, MW and kWp lesson, and a combined uncertainty of 7%. Illustrative figures, unrelated to any project.

An example with P50 and P90 scenarios
P501,314 MWh a year
Discount (1.282 × 7%)9%
P90 (1,314 × 0.91)1,196 MWh a year
Difference118 MWh a year

In 9 years out of 10, at least 1,196 MWh is expected. A very bad year can still fall below it: P90 isn't an absolute floor.

05

Where do you see it at Circular Urban?

Each solar project's sheet shows the estimated annual production from the design simulation. When a technical study reports scenarios, it helps to know which one a figure belongs to. It's a reference projection: real production depends on each year's weather and the project's performance.

  • Each solar project's sheet, in Energy Production: Annual Production.
  • Each solar project's sheet, in Risks & Mitigants.
06

What changes in your finances once you get it

You ask which scenario it is

Faced with a production figure, you check whether it's P50 or P90 before drawing conclusions.

You plan with a margin

You also run your numbers with the prudent scenario, so a weak year doesn't catch you off guard.

You read the gap

If P50 and P90 are far apart, the projection carries more uncertainty.

07

Common mistakes

Myth

P90 is the least the project can produce.

In reality

It's a value expected to be exceeded 9 years out of 10. In one year out of ten, production can fall below it.

Myth

P50 means the project runs at 50% of its capacity.

In reality

The 50 refers to probability, not capacity: it's the value exceeded in half the years.

Myth

If a year comes in below P50, the projection was wrong.

In reality

By definition, half the years are expected to fall below P50. What matters is the average over several years.

08

Test yourself

A project has a P50 of 2,000 MWh and a combined uncertainty of 5%. What is its approximate P90?

09

Keep learning

This content is educational. Every participation carries risks inherent to the project, including the possibility of partial or total loss, and results are subject to each project's actual performance.

Related projects

These are the Circular Urban projects where what you just read applies.

PPA Solar Energy - Subway La PintadaProject in Structuring

PPA Solar Energy - Subway...

Renewable Energy

La Pintada, Colombia

Total project value$146,747,250 COP
Min. Investment$500,000 COP
La Caucana Solar FarmProject in Structuring

La Caucana Solar Farm

Renewable Energy

La Pintada, Colombia

Total project value$5,687,197,597 COP
Min. Investment$500,000 COP
Need help?