What is AGGE (Large-Scale Self-Generation)?
Large-scale self-generation (AGGE) is when someone produces energy for their own consumption with a system above 1 MW. Past that limit it's no longer AGPE: connection studies are more demanding and selling the surplus follows rules closer to those of a power generator.
In 30 seconds
- It starts where AGPE ends: systems above 1 MW.
- With surplus up to 5 MW it has a simplified connection process (CREG 174 of 2021, updated by CREG 101 072 of 2025).
- The category changes the permits, the timelines and how surplus energy is sold.
Full guide
Solar surplus energy: how it is settled in Colombia
What happens to the solar energy you produce and don't use. CREG's three regimes, what the PDE and the AGPE limit are, and which one applies to you.
Read the guideWhy should you care?
Whether a project is AGPE or AGGE isn't a technical detail. It sets which permits it needs, how long it takes to connect and how it can sell its energy.
- You understand why two similar projects can have different schedules.
- You know what to ask about a large project's grid connection.
- You read the regulation section of a solar sheet with context.
Think of it as moving from a car to a truck
For a private car your usual license is enough. If you move up to a cargo truck, the vehicle does the same thing, it moves, but you need another license, more inspections and its own rules. Going from AGPE to AGGE is similar.
How does AGGE work?
- 1
The size is measured
Installed capacity is taken, which for solar systems is the sum of the inverters' AC output. If it exceeds 1 MW, it's AGGE.
- 2
The surplus is reviewed
The maximum power it will deliver to the grid is declared. Below 5 MW, the simplified process in CREG 174 of 2021 and CREG 101 072 of 2025 applies.
- 3
Connection studies are done
The network operator checks whether the local grid can take that energy and what changes are needed.
- 4
Sales rules are set
Surplus is sold under AGGE's own rules, closer to a generator's, not under the AGPE credit scheme.
An example with numbers
Three solar self-generation systems of different sizes. Illustrative figures, unrelated to any project.
| 0.08 MW (80 kW) rooftop | AGPE, simplest tier |
|---|---|
| 0.9 MW system | AGPE |
| 2 MW system with 1.5 MW surplus | AGGE, simplified process |
| 8 MW system with 6 MW surplus | AGGE, outside the simplified process |
The jump to AGGE doesn't change how the panels work. It changes the regulatory path to connect and sell energy.
Where do you see it at Circular Urban?
Each solar project's sheet sums up the rules that apply to it, including the CREG resolutions that set connection and surplus rules. There you can see which category the project falls under. Changes to those rules are a risk the sheet also describes.
- Each solar project's sheet, in Regulatory Framework: CREG Resolutions.
What changes in your finances once you get it
You place the project
With the system's capacity you know whether it's AGPE or AGGE and which rules govern it.
You expect realistic timelines
You know an AGGE project usually has longer connection studies and permits.
You look at regulatory risk
You check how it can sell its surplus and what would happen if those rules changed.
Common mistakes
- Myth
AGGE and AGPE are the same thing under another name.
- In reality
Both are self-generation, but the 1 MW limit separates different permits, studies and sales rules.
- Myth
An AGGE sells its energy just like a home solar rooftop.
- In reality
An AGPE rooftop gets credits or payments under CREG's small-scale scheme. An AGGE sells its surplus under rules closer to a generator's.
- Myth
Every AGGE goes through the same connection process.
- In reality
The simplified process applies when the power delivered to the grid is under 5 MW. Above that, generator rules apply.
Test yourself
A self-generation system has 1.2 MW of inverters and delivers at most 0.8 MW to the grid. Which category is it in?