Renewable Energy · Intermediate level · 3 min read ·
What is the SDL (Local Distribution System)?
The Sistema de Distribución Local (SDL), the local distribution system, is the part of the grid that carries energy to an area's users: lines and substations operating below 57.5 kV, at voltage levels 1, 2 and 3. The local grid operator runs it, and it is where almost every small and mid-sized solar project connects.
In 30 seconds
- It groups voltage levels 1, 2 and 3, below 57.5 kV.
- Each area's grid operator runs it and approves connections.
- Distributed generation projects connect to the SDL, not to national transmission.
Why should you care?
A solar project can be built and still deliver no energy if its connection isn't approved. The SDL's operator grants that approval, and its timelines go into the schedule.
- You know who decides whether and when a project can connect.
- You understand why local grid capacity matters as much as sunshine.
- You read the voltage level on a technical sheet with judgment.
Think of it as a neighborhood's streets
Highways move traffic between cities; neighborhood streets take it to each door. The SDL is those streets. A small solar project enters through a neighborhood street, not the highway, and needs permission from whoever manages those streets.
How does the SDL work?
- 1
Transmission reaches the region
Energy travels on the national transmission system, at 220 kV or more, and the regional one, between 57.5 and 220 kV.
- 2
The SDL distributes it
Substations step the voltage down and level 3, 2 and 1 networks carry it to neighborhoods, shops and industry.
- 3
The project applies to connect
It files its request with the grid operator, which checks whether the circuit has available capacity.
- 4
It is approved and connected
With the connection approved and legalized, the project delivers its energy to the SDL and through it to the rest of the system.
An example with numbers
The voltage level at which systems of different sizes usually connect. Reference values; each grid operator sets the exact connection point.
| Level 1 (under 1 kV) | A home rooftop, about 5 kWp |
|---|---|
| Level 2 (1 to 30 kV) | A shop or warehouse, tens or hundreds of kWp |
| Level 3 (30 to 57.5 kV) | Large industry or a plant of a few MW |
| Level 4 and STN (57.5 kV or more) | No longer SDL: regional or national transmission |
The bigger the system, the higher the voltage it usually connects at. Distributed generation projects usually connect on levels 1 and 2 of the SDL.
Where do you see it at Circular Urban?
Each solar project connects to the network of its area's grid operator, which is part of the SDL. The sheet shows who that operator is, where the connection stands and what risks the connection schedule carries.
- Each solar project's sheet, under How the operation flows, where the grid operator appears.
- Each solar project's sheet, under Risks & Mitigants.
What changes in your finances once you get it
You look at the connection, not just the panels
You check whether the grid operator has already confirmed the connection is viable.
You allow for timelines
You know legalization with the grid operator takes weeks and can move the start of operation.
You understand the circuit's limits
A circuit with little spare capacity can limit how much energy the grid takes at certain hours.
Common mistakes
- Myth
A solar project connects straight to the national high-voltage grid.
- In reality
Small and mid-sized projects connect to the SDL, the local grid, through the grid operator.
- Myth
Once the panels are installed, the project can deliver energy.
- In reality
It first needs its connection approved and legalized by the grid operator.
- Myth
The SDL and the grid operator are the same thing.
- In reality
The SDL is the physical network; the grid operator is the company that runs and maintains it.
Test yourself
A line operates at 13.2 kV. Which part of the grid does it belong to?