Renewable Energy · Intermediate level · 3 min read ·

What is the SDL (Local Distribution System)?

The Sistema de Distribución Local (SDL), the local distribution system, is the part of the grid that carries energy to an area's users: lines and substations operating below 57.5 kV, at voltage levels 1, 2 and 3. The local grid operator runs it, and it is where almost every small and mid-sized solar project connects.

In 30 seconds

  • It groups voltage levels 1, 2 and 3, below 57.5 kV.
  • Each area's grid operator runs it and approves connections.
  • Distributed generation projects connect to the SDL, not to national transmission.
01

Why should you care?

A solar project can be built and still deliver no energy if its connection isn't approved. The SDL's operator grants that approval, and its timelines go into the schedule.

  • You know who decides whether and when a project can connect.
  • You understand why local grid capacity matters as much as sunshine.
  • You read the voltage level on a technical sheet with judgment.
02

Think of it as a neighborhood's streets

Highways move traffic between cities; neighborhood streets take it to each door. The SDL is those streets. A small solar project enters through a neighborhood street, not the highway, and needs permission from whoever manages those streets.
03

How does the SDL work?

  1. 1

    Transmission reaches the region

    Energy travels on the national transmission system, at 220 kV or more, and the regional one, between 57.5 and 220 kV.

  2. 2

    The SDL distributes it

    Substations step the voltage down and level 3, 2 and 1 networks carry it to neighborhoods, shops and industry.

  3. 3

    The project applies to connect

    It files its request with the grid operator, which checks whether the circuit has available capacity.

  4. 4

    It is approved and connected

    With the connection approved and legalized, the project delivers its energy to the SDL and through it to the rest of the system.

04

An example with numbers

The voltage level at which systems of different sizes usually connect. Reference values; each grid operator sets the exact connection point.

An example with the SDL
Level 1 (under 1 kV)A home rooftop, about 5 kWp
Level 2 (1 to 30 kV)A shop or warehouse, tens or hundreds of kWp
Level 3 (30 to 57.5 kV)Large industry or a plant of a few MW
Level 4 and STN (57.5 kV or more)No longer SDL: regional or national transmission

The bigger the system, the higher the voltage it usually connects at. Distributed generation projects usually connect on levels 1 and 2 of the SDL.

05

Where do you see it at Circular Urban?

Each solar project connects to the network of its area's grid operator, which is part of the SDL. The sheet shows who that operator is, where the connection stands and what risks the connection schedule carries.

  • Each solar project's sheet, under How the operation flows, where the grid operator appears.
  • Each solar project's sheet, under Risks & Mitigants.
06

What changes in your finances once you get it

You look at the connection, not just the panels

You check whether the grid operator has already confirmed the connection is viable.

You allow for timelines

You know legalization with the grid operator takes weeks and can move the start of operation.

You understand the circuit's limits

A circuit with little spare capacity can limit how much energy the grid takes at certain hours.

07

Common mistakes

Myth

A solar project connects straight to the national high-voltage grid.

In reality

Small and mid-sized projects connect to the SDL, the local grid, through the grid operator.

Myth

Once the panels are installed, the project can deliver energy.

In reality

It first needs its connection approved and legalized by the grid operator.

Myth

The SDL and the grid operator are the same thing.

In reality

The SDL is the physical network; the grid operator is the company that runs and maintains it.

08

Test yourself

A line operates at 13.2 kV. Which part of the grid does it belong to?

09

Keep learning

This content is educational. Every participation carries risks inherent to the project, including the possibility of partial or total loss, and results are subject to each project's actual performance.

Related projects

These are the Circular Urban projects where what you just read applies.

PPA Solar Energy - Subway La PintadaProject in Structuring

PPA Solar Energy - Subway...

Renewable Energy

La Pintada, Colombia

Total project value$146,747,250 COP
Min. Investment$500,000 COP
La Caucana Solar FarmProject in Structuring

La Caucana Solar Farm

Renewable Energy

La Pintada, Colombia

Total project value$5,687,197,597 COP
Min. Investment$500,000 COP
Need help?