What is the CAPEX of a solar project?
The CAPEX of a solar project is everything it costs to get the system ready to produce: panels, inverters, mounting, wiring, installation, studies, permits and grid connection. It is paid once, at the start. Divided by installed capacity it gives the cost per kWp, the measure for comparing projects of different sizes.
In 30 seconds
- It is the upfront investment; the costs of running the system are separate, in OPEX.
- Modules are one of the largest items, but the rest of the system, the works and the permits usually weigh more together.
- Cost per kWp lets you compare projects of different sizes.
Why should you care?
Almost all of a solar project's money is spent before it produces its first kWh. That's why CAPEX weighs so much on the project's result.
- You understand where the construction money goes.
- You compare projects by cost per kWp, not by the total.
- You see why CAPEX sets much of the cost of energy (LCOE).
Think of it as fitting a new kitchen
The appliances are what you notice, but you also pay for cabinets, pipes, wiring, labour and the building permit. All of that is paid once. The monthly gas and power bills come later, and they are something else.
How does the CAPEX of a solar project work?
- 1
Main equipment
Solar modules and inverters. Modules are usually the largest item in the budget.
- 2
Mounting and balance of system
Racking, wiring, protections, switchboards and, if needed, a transformer. It's the least visible part and it weighs a lot.
- 3
Installation and works
Electrical and civil labour, transport and on-site assembly.
- 4
Studies, permits and connection
Design, the connection study with the network operator, RETIE certification and the other steps before energizing.
- 5
Cost per kWp
Divide total CAPEX by installed capacity to compare projects of different sizes.
The formula
Cost per kWp = CAPEX ÷ Installed capacity (kWp)
- CAPEX
- = total cost of getting the system ready to produce
- Installed capacity
- = sum of all panels' peak power, in kWp
An example with numbers
An illustrative 1 MWp (1,000 kWp) project with a CAPEX of 1,000 units. The split is a reference; every project has its own.
| Solar modules (35%) | 350 units |
|---|---|
| Inverters (10%) | 100 units |
| Mounting, wiring and protections (30%) | 300 units |
| Installation and works (15%) | 150 units |
| Studies, permits and connection (10%) | 100 units |
| Cost per kWp (1,000 ÷ 1,000) | 1 unit per kWp |
In this illustrative split, 65% of CAPEX goes on things other than panels. A 2 MWp project with a CAPEX of 1,800 units costs more in total but less per kWp: 0.9.
Where do you see it at Circular Urban?
Each solar project's sheet shows the total investment next to the installed capacity and the equipment, so you can work out the cost per kWp yourself. The figures are reference projections and not binding.
- Each solar project's sheet, under Financial Models: Total Investment.
- Under Technical Specifications: DC Capacity, Solar Modules and Inverters.
- Under Tax Benefits — Law 1715: the special 50% CAPEX deduction.
What changes in your finances once you get it
You compare per kWp
Two projects of different sizes are compared by dividing their CAPEX by their capacity, not by looking at the total.
You keep CAPEX and OPEX apart
CAPEX is paid once to build; each year's maintenance, insurance and operation are OPEX.
You ask about what you can't see
Grid connection and permits can stretch construction timelines. It's worth knowing what stage they are at.
Common mistakes
- Myth
CAPEX is just the price of the panels.
- In reality
Modules are only one part. The rest goes on inverters, mounting, wiring, works and permits, which together usually weigh more.
- Myth
A bigger project always costs more per kWp.
- In reality
Usually the opposite: the fixed costs of design, permits and connection are spread over more kWp.
- Myth
CAPEX is paid every year.
- In reality
It is paid once, to build. Each year's costs are OPEX, although a large replacement, such as an inverter, may be booked separately.
Test yourself
A 500 kWp project has a CAPEX of 600 units. What is its cost per kWp?